Professional · Miron Construction · May–August 2026
Concrete Sequencing & Formwork
At the Oshkosh Wastewater Treatment Plant, I supported the team’s concrete pour sequencing and formwork documentation using BIM²form for Revit. My colleague NJG led this task and is credited as the drawing author.
- My contribution
- Team support for concrete pour sequencing & formwork documentation · Led by colleague NJG
- Tools used here
- Revit · BIM²form
Internship contribution within Miron Construction’s project teams
03 · Featured work · Concrete formwork & sequencing
Concrete,
pour by pour.
At the Oshkosh Wastewater Treatment Plant, I helped the team visualize a complex concrete pouring sequence using BIM²form, a formwork plug-in for Revit. We connected individual pour phases to plans, 3D views, and schedules. My colleague NJG led this task and is credited as the drawing author on the sheets; the material shown here represents a team effort I supported, not work I completed alone.

A color-coded sequence locates each pour within the overall building. Phase-specific sheets bring concrete quantities, panel layouts, elevations, and formwork components into one coordinated view.
From Overall Sequence to Formwork Detail
Selected sheets · Select an image to expand
MC001 · Overall sequence & formwork schedulesExpand +Close −
MC104.1 · W04A wall & formwork coordinationExpand +Close −
Miron Construction · Preliminary — Not for Construction. Shown as evidence of my contribution to the team’s planning and coordination work, not as a final construction instruction.
View Complete Sheet SetHide Complete Sheet Set26 Sheets · Preliminary · Not for Construction
For demonstration purposes only. Do not copy, reproduce, or use these drawings. Not for construction.