Professional · Miron Construction · May–August 2026

Steel Sequencing · SYNCHRO 4D

I developed the steel sequences from the project’s P6 schedule and Revit model, bringing schedule and model information together through Navisworks and SYNCHRO 4D to show planned installation over time.

My contribution
End-to-end sequence development from the project’s P6 schedule and Revit model
Tools used here
SYNCHRO 4D · Navisworks · P6

Internship contribution within Miron Construction’s project teams

01 · Featured work · SYNCHRO 4D

Construction,
over time.

For UW–Whitewater’s Winther and Heide Hall work, I developed the complete steel sequences from the project’s P6 schedule and Revit model. Using Navisworks and SYNCHRO 4D, I connected model geometry with planned installation activities and built the paired views, active-task display, and timeline shown here. The building design and source schedule were project inputs, not my authorship.

Motion study Play to explore ↘
Winther Hall · SYNCHRO 4D steel sequence · 38 sec · Silent

Companion sequence

Heide Hall

A second sequence shows the steel frame progressing through the building’s levels, with the same relationship between tasks, time, and model geometry.

Motion study Play to explore ↘
Heide Hall · SYNCHRO 4D · 22 sec · Silent